|
The Present High School
As published in "The City of Kenosha and Kenosha County Wisconsin: A Record of Settlement,
Organization, Progress and Achievement" by Frank H. Lyman Vol. 1, The S. J. Clarke Publishing Co.,
Chicago, 1916. p. 193
In January, 1890, the council voted an appropriation of $10,000 for a new high school. After
considerable disagreement over the selection of an architect, F. S. Allen was finally chosen, March
4, 1890. On March 5th, the heating and ventilating system was settled upon, the Ruttan system being
chosen, after a committee of the board had visited Chicago and Rockford to investigate; contract,
$2,100. In May, Mr. Allen submitted plans and specifications. On June 5th, bids from five
contractors, two local and three out of town, were received. Later all bids were rejected, and
plans for a smaller building called for. The first plans anticipated future needs, and their
rejection was a mistake, fully demonstrated before the lapse of half a decade. Only one bid was
received upon Mr. Allen's modified plans, that of Wm. M. Rowe of Kenosha. He was awarded the
contract, for $34,810, with an allowance for the old building of $900.
The treasurer's record of these days cannot be found; but examination of the minutes of the board
produces items, for the various expenses of construction, including the architect's fees, and
seating ($1,500), which amount to $45,500. This may be taken as a fairly accurate figure, for the
original structure.
At commencement time in 1891, the building was sufficiently near completion to admit of the
exercises being held there. When first occupied, the lower floors and two class rooms in the second
floor were used for the grades. As high school demands increased, the grade rooms on the second
floor were made into an assembly room, by the removal of a partition. The grades were confined to
the first floor. In 1894, the auditorium was seated with opera chairs, at a cost of $400, and in
1905 some needed sanitary changes were made at an additional cost of $2,325. Total cost of building
to this date, 1905, $47,200.
In June, 1905, the board began considering the enlargement of the high school building. An addition
to the west side was erected in 1906 and 1907. The plans and specifications were prepared by T.
Gaastra, and the contract was awarded to Theleen & Anderson, for $20,600. The construction included
the extension of the auditorium over the new wing, making it a large room, 50 ft. by 160 ft.,
suitable for entertainments, and, as it was at first hoped, for athletic events. The heating plant
for the new part cost $2,800. Other expenditures, including architect's fees, supervision of
construction bell system, gas fitting and extras, added fully $5,000 more. Total cost of addition
must have been in the neighborhood of $28,400, and the total cost of the high school with the
addition, $75,600.
In 1911, rumors of unsafe conditions in the high school were heard. It was believed that this
condition was due to the great stretch of heavy slate roof. The school board ordered an
investigation, engaging for this purpose, Mr. Balzar, city engineer of Kenosha. The work he
recommended was duly carried out under his direction by John Bruns, at an expense of $1,680.
In February, 1913, one of the contractors for the 1906-07 addition sent a communication to the
board urging further efforts to make the auditorium of the high school safe. The board, desirous of
doing whatever was necessary to make the building a safe place, ordered another investigation. This
was made by H. H. Hahn, assisted by Engineer Schott and by Mr. Giest, consulting engineer from
Milwaukee.
The resulting report, which is in the minutes of the board for February 30 [sic], 1913, justified
the complaint, and immediate action was taken. A contract was let to Gottlieb Schaeffer for
removing the heavy slate roof which constituted the menace. This was done and the floor area of the
auditorium reduced to the size it had in the original structure. The cost of this repair and
reconstruction was $2,800. This reduced auditorium is now partitioned off into four classrooms,
this change costing about $650.
It is this seen that the high school building as it stands today has cost the city of Kenosha
nearly $81,000.
|