resources in the archives room the juniata county covered bridge tour POMEROY-ACADEMIA BRIDGE RESTORATION
|
POMEROY-ACADEMIA BRIDGE RESTORATION Funding for the restoration of the Pomeroy Academia Covered Bridge has come from various sources. The Pennsylvania Historical and Museum Commission was the first to award a $70,000 Keystone Preservation Grant; the Pennsylvania Department of Economic and Community Development awarded $32,000; the Theodore Burr Covered Bridge Society donated $2,000. The Society raised in excess of $60,000 from private donors and fund raising efforts and received a low interest Infrastructure Bank Loan through the Pennsylvania Department of Transportation to fund the remaining portion of the pre-construction costs of $209,000. The construction costs will be funded by Transportation Enhancement funding received through SEDA-COG and the Pennsylvania Department of Transportation. Beale Twp approach to the bridge before any work began. An architectural design detail on the bridge, Beale Twp side.
Orange X's mark timbers that cannot be utilized in the reconstruction. Preparation of the causeway so that support shoring can be erected. Causeway construction looking to the Beale Twp side. Site preparation on the Spruce Hill Twp side for causeway construction
This photo is from the Spruce Hill Twp side of the bridge and shows site preparation.
The first step in dismantling the bridge was removing the siding.
A view of the bridge from afar without it's siding.
A view of the bridge from Beale Twp side without its siding.
Erecting support shoring Beale Twp side.
A view of the support shoring; siding removed from bridge.
A view of the pier and the Spruce Hill side abutment.
A view of the Beale Twp abutment with the shoring in place.
Roof removal; first step is to remove the cross braces.
Quitting time; covering the structure against the elements. Roof removal started on the Beale Twp side of the bridge. A view of the roof being removed from the side.
In this view all of the support structure of the roof has been removed.
A view from the side - Beale Twp.
Closer view of the roof removal.
Roof removal Beale Twp side complete for this small section.
A view of the causeway built into the streambed;
First phase of removing the deck;
Close up showing timbers resting in the stone abutment.
Close up of the support structure under the deck.
Prying the deck boards loose.
Abutment fissure, Beale Twp side to be repaired.
At work removing loose grout.
At work removing loose grout.
Wing wall showing loose grout and stones.
Wing wall repointed.
Removing tie beams.
Crane removing tie beam.
Crane removing tie beam.
Stacking tie beams to for move to work site. Removal of the inside arch on the right side, Beal Twp. side of bridge. Removal of the inside arch on the left side, Beale Twp. side of bridge. Removing floor beams Beale Twp. side. View of underside of the bridge, Beale Twp. side, removing floor beams. Removing top chord. Removing vertical supports. Removing the bottom chords. Shoring supporting the bottom chords, Beale Twp. side. View of bridge downstream showing the remaining timbers to be removed, Beale Twp. side. View of the remaining timbers to be removed on the Beale Twp. side. Removing the top lateral beams on the Spruce Hill Twp. side. Temporary shoring supporting the Spruce Hill Twp. side. Removing bottom cross braces Spruce Hill Twp. side. Spruce Hill Twp. side with bottom braces removed. Underside of the Spruce Hill Twp. side of the bridge, bottom braces removed. Removing the bottom chords on the Spruce Hill Twp. side. Downstream view of the remaining timbers to be removed from the Spruce Hill Twp. span. The Pomeroy Academia Bridge dismantled. Newly pointed abutment Beale Twp. side. Close up of newly pointed abutment. Wood from the bridge stacked and labeled ready to be reused. Wood from the bridge stacked and labeled ready to be reused. Wood from the bridge stacked and labeled ready to be reused. On the Beale Twp. side of the bridge, the metal culvert over the defunct mill race was faced with stone giving it a much improved appearance. Concrete collars were poured around both abutments and the pier to decrease the scouring effects of water flow. Commencing the rebuilding of the bridge beginning on the Spruce Hill Twp. side. The Beale Twp. side begins
On behalf of the Juniata County Historical Society I would like to thank Gary Shingledecker, the onsite Bridge engineering inspector, for his contribution of pictures to this web page; and most importantly to Michael Milliken, our volunteer web page manager, for his time, diligence and devotion to the construction of the Pomeroy Academia Covered Bridge Restoration page. All written content and photos �2001-2009
Juniata County Historical Society, all rights reserved.
|